View Issue Details

IDProjectCategoryView StatusLast Update
000946140001: MachineryDocumentation Erratapublic2025-07-07 13:13
ReporterTonja Heinemann Assigned ToWolfgang Mahnke  
PrioritynormalSeverityminorReproducibilityalways
Status resolvedResolutionfixed 
Summary0009461: typo in Annex C - RPI <-> PRI
Description

In Annex C, table 53 in the last column there are two entries saying
"SPLIT in setup time (AUST) and value added production time (APT=PQ*RPI) as retrograde confirmation (backflush) "

and note 3 says:
Note 3: If an added value activity is included in setup mode period, then the added value time has to be calculated as APT (APT=PQ*RPI) based on produced quantities and AUST has to be reduced based on this calculated APT.

This should likely say "PRI" (planned runtime per item) instead of RPI in both instances to use the terminology of ISO 22400.

TagsNo tags attached.

Activities

Heiko Herden

2025-07-07 13:12

manager   ~0023084

Already fixed by Wolfgang for the next publication.

Wolfgang Mahnke

2025-07-07 13:13

developer   ~0023085

Fixed in version 1.05 (still draft at the moment)

Issue History

Date Modified Username Field Change
2024-03-11 19:05 Tonja Heinemann New Issue
2025-07-07 13:12 Heiko Herden Note Added: 0023084
2025-07-07 13:12 Wolfgang Mahnke Assigned To => Wolfgang Mahnke
2025-07-07 13:12 Wolfgang Mahnke Status new => assigned
2025-07-07 13:13 Wolfgang Mahnke Status assigned => resolved
2025-07-07 13:13 Wolfgang Mahnke Resolution open => fixed
2025-07-07 13:13 Wolfgang Mahnke Note Added: 0023085