View Issue Details

IDProjectCategoryView StatusLast Update
000648030170: ODVA-CIP: 02: User StoriesExternally Communicatedpublic2021-02-16 01:02
ReporterGreg Majcher Assigned To 
PrioritynormalSeverityminorReproducibilityhave not tried
Status newResolutionopen 
Summary0006480: Brownfield Installation Improvement with Regulations (5.14)
Description

As a Plant Manager responsible for a pharmaceutical production operation that is currently validated by the Food & Drugs Agency (FDA) I am being tasked to provide additional data from my processes to support Good Manufacturing Practices (GMP), facilitate an energy management campaign for ISO 50001, and other overall operational improvements.

This data includes asset , diagnostic and process data. Asset data can include things like device type codes, revisions, catalog, and serial numbers. Diagnostic data may include alarms, fault codes, memory faults, etc. Process data would be values such as pressure, flow, temperature, etc.

My current system has CIP devices with interesting data that I can use. I may also need to add a third-party device (non-CIP) to my network for additional data. I would need a gateway to collect this data and send it to a cloud for monitoring and analysis.

A variance to the risk assessment for validation protocol can be written since we are not modifying/changing the control program, any devices or functionality to the production operation. It is important that we do not have to undergo revalidation to save time and costs while retaining optimal uptime.

It is necessary to have a gateway that is secure, does not receive inputs from the cloud, only pulls data from devices, and pushes it to the cloud. This should not impact the validated process and equipment and provide a risk-free way of data collection for analysis. There must be no programming or commissioning changes required at the PLC/DCS.

TagsNo tags attached.
Boundary Conditions
Success Criteria

Relationships

parent of 0006178 feedback 30170: ODVA-CIP: 03: Requirements Asset Management Information 
parent of 0006481 feedbackGreg Majcher 30170: ODVA-CIP: 03: Requirements Ability to report process data 
parent of 0006482 feedbackGreg Majcher 30170: ODVA-CIP: 03: Requirements Gateways must expose the amount of OPC traffic that is added to a CIP network 
parent of 0006483 feedbackGreg Majcher 30170: ODVA-CIP: 03: Requirements Gateways must have the ability to prevent write capability from OPC 
parent of 0006484 feedbackGreg Majcher 30170: ODVA-CIP: 03: Requirements Gateways must be able to limit traffic 
related to 0005911 new 30170: ODVA-CIP: 02: User Stories Common Diagnostic View (5.9) 
Not all the children of this issue are yet resolved or closed.

Activities

There are no notes attached to this issue.

Issue History

Date Modified Username Field Change
2021-02-15 22:23 Greg Majcher New Issue
2021-02-15 22:25 Greg Majcher Relationship added parent of 0006178
2021-02-15 22:27 Greg Majcher Relationship added related to 0005911
2021-02-15 22:34 Greg Majcher Relationship added parent of 0006481
2021-02-15 22:38 Greg Majcher Relationship added parent of 0006482
2021-02-16 00:59 Greg Majcher Relationship added parent of 0006483
2021-02-16 01:02 Greg Majcher Relationship added parent of 0006484